Project History
IPSCO Steel (Alabama) Inc.
230/34.5 kV MVA Main Substation, Design, Supply and Installation
Design Build of 230/34.5 kV substation and components including
230 kV circuit switchers
34.5 kV SF6 outdoor circuit breakers
6.20 Mvar filters, mimic protection and control panels
Control building, foundation, overhead aluminum bus and structures
Site grading, oil containment system, grounding and fencing
IPSCO STEEL (Alabama) Inc. Kvaerner Metals
Power Distribution Electrical
Installation of all 34.5 kV cable feeders and terminations
Installation of unit substations, transformers, switchgear, control components, and protection components, including oil filled and dry type transformers
34.5 kV vacuum circuit breakers and disconnect switches, 34.5 kV 4160V and 480V distribtion components
Custom bus installation
IPSCO Steel (Alabama) Inc. International Mill Service
Scrap & Slag Facility
Installation Hi-Mast Lighting and electrical track switches
Installation of sight utilities
Design and installation of custom underground cable duct banks
Installation of control and distribution components
IPSCO Steel (Alabama) Inc. Kvaerner Metals
Hi-Bay Lighting, Design, Supply & Installation
Lighting design and installation of all high back lighint in the following areas
Meltshop
Caster
Rolling Mill
Plate Mill
IPSCO Steel (Alabama) Inc. Kvaerner Metals
Electrical Installation Communications Phase 2
Installation and termination of plant telephone, fribre-optics, ethernet and commincations systems
ISPCO Tubulars Inc. Camanche, Iowa
Finishing & Testing Area Equipment Upgrades & Improvements
Whip conveyor installation
Wire MCC
Installation of HSS conveyor
Fabrication and installation of HSS Control Station
Ipsco Inc.
Ladle Metallurgical Furnace Transformer Installation
Installation of 25MVA 15kV Ladle Metallurgical Furnace transformer feeding a twin LMF
Installation and wiring power protection and control elements
Installation, wiring and commissioning of alloy conveyance and weighing equipment
Caribbean Utilities Company
15 kV Cable Installation
Detail design and installation of 15kV cable system in a utility substation
Incorporation of 32 runs of 1500 feet through a complex underground ductbank system and 5 precast concrete manholes
Development of installation procedures using custom sheave arrangements to install 3 single conductor concentric neutral cables in the underground ductank systems whule adhering to manufacture's specification on cable tensions and side wall pressure limits
IPSCO Inc. Transfer Industries
SpiralControl & Power System Upgrade
Installation of all control and distribution components
Installation of 3 1500 kVA substations and 1 1000 kVA substation
Renovations to a 10 MVA, 138/13.8kV substation
Installation of AC variable speed drives
Renovations to AC & DC welders to allow for remote PLC control and monitoring
IPSCO Inc.
24" Mill Installation - New constructor
Installation of a 138/13.8kV 10 MVA substation and all associated cables
Installation of 6 1500 kVA substations
Installtion of 480V distribution switchgear
City of Regina
Water Treatment Facility
Motor Control Installation
Contril & Instrumental Design
IPSCO Tubulars Inc. Camanche, Iowa
Electical Installation of Hydro Modications
Installation of hydro tester midifications
Electrical installation of gangsaws
Carribean Utilities Company Aea Brown Boveri
Installation of High Voltage Cable
Installation of 69kV cables from transformers to 15kV swtichgear and generators complete with termination
Installation of 69kV cable from GIS switchgear to unit sub transformers complete with terminations
IPSCO Inc.
Static Var Compensator Installation
Installtion and commissioning of all elements of a 15 mV, 70 Mvar SVC
Design and installation of 15kV feeders using custom cable configurations tied to furnace buses
IPSCO Inc.
New High Speed Pipe Mill, Blytheville, Arkansas
Wiring of automation equipment
IPSCO Inc.
LaminarFlow Upgrade
Installation of 3 MVA Substation
Installation of 4-400 hp A.C. Variable speed drives for low pressure, high volume water pumping system
IPSCO Inc.
Fast Tracked Upgrade of 50 MVA to 65 MVA Arc Furnace Transformer
Co-ordination of All Electrical and Mechanical Services for Removal of 50 MVA Arc Furnace Transformer and Replacement with 65 MVA
Oversee Fabrication and Installation of an Adapter Base
Co-ordination of Installation of Components During 24 Hour Production Periods
Design and install 15 kV cable system for new transformer
IMC-Kalium
15kV and 5kV Cable Installation
Troubleshooting, Consulting and repair to existing faulted calbes
Emergency Back-Up Generator Installation
Design and Installation of Pneumatic Controls
IPSCO Inc.
Addition of 3-1600 HP Fan Motors
Design and Installation of Cable and Control Components for Motors and Fans
Mechanical Installation of Drop Boxes, Conveyors and Blastgates as well as Ducting
IPSCO Inc.
72kV Substation Renovation
Installation and commissioning of 2-1600 hp 6.9kV Fan Motors
Design and Installation of 3000 AMP Cable Feeder, Breaker, Protection Elements
IPSCO Inc.
24" ERW Mill 138kV Substation Construction
In Charge of All civil work
Site Grading
Pile Foundations
Soil Resistivity
Fabrication of all Steel Structures
Substation Erection
Installation of aHigh Voltage CT's and PT's and Related Structures
Installation of Transformer and Subsequent Testing
Fabrication ans Installation of Control Builings and Equipment
Imbedded Conduits and High Voltage Duct Banks
IPSCO Inc.
Finish Mill Expansion
Istallation of new 6.9kV switchgear and associated cables
Installation of a thrid 4500 hp dc mill motor and parallelling controls
Installation of dc drives for motors up to 1500 hp
Installation of PLC and control components
Commissioning of all control and power components